So from the completion of the frame on 11th of November, the builders have today completed the brickwork, so thats just under a month, of which they worked about 2 weeks solid due to rain delays etc.






 

The builders have even done a partial clean of the interior.

So from what we've been told the brick cleaners are on site next week and then the downpipes etc will go on around the same time as the roof, hopefully all before Christmas depending of the wild sydney weather.