Lockup done, practical completion here we come!

So I've been slack and busy as hell recently so the blog hasn't had any real attention paid to it.

So here is the update since December.  The house has come along very well, the roof was finished and a partial colour completed on the exterior (second colour and final touchup to occur later I guess).  Then in mid Feb there appeared the wiring and then insulation and shortly there after the platerers were on site.  Amazingly it took less than 2 days for the team of 7 to do the whole house, now thats efficient for you.

At the start of this week the carpenter appeared on site and we met with him on Thursday morning first thing to site the front door lock and had a look around. Wow the kitchen was almost complete and most internal doors were on, he said they would be finished by next Wednesday and then the tilers would start.

Very happy with the progress, considering the contracted period ends on 25 May and the progress in the last two weeks I'd have to say they appear to be ahead of schedule which is great, now if only they can keep it up!

No comments:

Post a Comment